Project Description:
PBC Project No. 07115
Engine Company 115
119th and Morgan Street
The PBC will award a design-build contract for the Project in accordance with the requirements of Sections 20.3 through 20.20 of the Public Building Commission Act (50 ILCS 20/et seq.). Per the Act, this will be a two-phase procurement process. This two-phase process will evaluate design-build entities based on qualifications, technical approach, and cost proposals for the following design-build project:
The Project requires the design and construction of a new Engine Company 115; associated environmental site remediation, site preparation, new building construction and site development, including new monopole and utilities, as required.
PHASE I
Phase I – Submission Due Date:
Submittals must be delivered by January 22, 2019 at 1:00p.m. (CST) (updated via Addendum No. 4) to the attention of Patricia Montenegro, Public Building Commission of Chicago, Richard J. Daley Center, 50 West Washington Street, Room 200, Chicago, IL 60602.
Phase I – Pre-Submission Conference:
A pre-submission conference will be held on Thursday, January 10, 2019, 10:00 a.m. at the following location:
The Salvation Army – Ray and Joan Kroc Corps Community Center – Celebration Room
1250 West 119th Street
Chicago, IL 60643
Firms interested in submitting responses are strongly encouraged to attend.
Phase I – Pre-Submission Materials:
- Pre-submission Conference Attendance Sign-in Sheet
- Pre-submission Conference Agenda
- Pre-submission Conference Presentation
Phase I – RFP Document:
RFP Document for Design/Build Services for Engine Company 115 – Issued December 7, 2018
- RFP Exhibit A – Sample Form of Design Build Agreement
- RFP Exhibit B – Insurance Requirements
- RFP Exhibit C – Sample Project Community Area Map
- RFP Exhibit D – Sample Chicago Public School Project Labor Agreement
- RFP Exhibit E – Draft Program Summary
- RFP Exhibit F – Traffic Study (Draft)
- RFP Exhibit G – Geotechnical Report (Draft)
- RFP Exhibit H – Environmental Report
- RFP Exhibit I – Boundary/Alta Survey
- RFP Exhibit J – Zoning Analysis
- RFP Exhibit K – PD/Entitlement Submission Requirements and Conceptual Drawings
Phase I Addenda:
- Addendum No. 1 for Design-Build Services for Engine Company 115 can be obtained by clicking on the following links:
- Addendum 1 – Issued January 8, 2019
- Addendum No. 1 – Table of Contents
- Addendum No. 1 – Exhibit G. Geotechnical Report (Final)
- Addendum No. 1 – Exhibit L. Ground Penetrating Radar & Electromagnetic Induction Survey
- Addendum No. 1 – Exhibit M. Test Pit Investigation
- Addendum No. 1 – Exhibit N. Comprehensive Site Investigation Report/Remediation Objectives Report/Remedial Action Plan Report (Draft)
- Addendum No. 1 – Exhibit O. House Number Certificate
- Addendum 1 – Issued January 8, 2019
- Addendum No. 2 for Design-Build Services for Engine Company 115 can be obtained by clicking on the following link: Addendum 2 – Issued January 15, 2019
- Addendum No. 3 for Design-Build Services for Engine Company 115 can be obtained by clicking on the following link: Addendum 3 – Issued January 16, 2019
- Addendum No. 4 for Design-Build Services for Engine Company 115 can be obtained by clicking on the following link: Addendum 4 – Issued January 17, 2019
PHASE II
Shortlisted Firms:
Shortlisted Firms for Design-Build Services for Engine Company 115 can be obtained by clicking on the following link: Engine Company 115 Shortlisted Firms
Follow this project on Twitter PBCChi#DBforEC115
Public Building Commission of Chicago
Mayor Rahm Emanuel, Chairman
Carina E. Sánchez, Executive Director
Office of Inspector General Complaint Hotline
If you see corruption, fraud, waste, or dishonest practices of any kind please report it to the City of Chicago Office of Inspector General (OIG) – PBC’s oversight body. Concerned employees, contractors, consultants, and members of the public may contact OIG via its independent hotline and website.
Telephone Reporting: (866) IG-TIPLINE (866-448-4754).
Web Reporting: http://ChicagoInspectorGeneral.org/Get-Involved