Second Floor Board Room, Richard J. Daley Center, 50 W. Washington Street
| Attachments |
| Minutes | Agenda | Presentation | Summary |
| Change Order Approved | |
| Project: | William Jones College Prep Site Prep (Caissons) |
| Address: | 700 South State Street |
| Contractor: | Rausch Construction Co., Inc. |
| Amount: | 474819.49 |
| Reason: | Multiple see below |
| Contract Number: | 1528 |
| Date: | 8/14/2012 |
| Notes: |
|
| Project: | William Jones College Prep Site Prep (Excavation) |
| Address: | 700 South State Street |
| Contractor: | Roy Strom Excating & Grading Company |
| Amount: | 3367.09 |
| Reason: | Other |
| Contract Number: | 1532 |
| Date: | 8/14/2012 |
| Notes: | |
| Project: | 31st Street Harbor – Coastal |
| Address: | 3155 South Lake Shore Drive |
| Contractor: | Paschen Gillen Skipper Marine Joint Venture |
| Amount: | 28109.27 |
| Reason: | Other |
| Contract Number: | 1502R |
| Date: | 8/14/2012 |
| Notes: | |
| Project: | South Shore High School Abatement & Demolition |
| Address: | 7529 South Constance Avenue |
| Contractor: | Omega Demolition Corporation |
| Amount: | -134000.00 |
| Reason: | Other |
| Contract Number: | 1525 |
| Date: | 8/14/2012 |
| Notes: | |
| Project: | Edgebrook Elementary School Addition |
| Address: | 6525 North Hiawatha |
| Contractor: | Henry Bros. Company |
| Amount: | 183721.44 |
| Reason: | Other |
| Contract Number: | 1524 |
| Date: | 8/14/2012 |
| Notes: | |
| Project: | Engine Company 109 |
| Address: | 2343 South Kedzie Avenue |
| Contractor: | George Sollitt Construction/Oakley Construction JV |
| Amount: | 264769.12 |
| Reason: | Other |
| Contract Number: | 1495 |
| Date: | 8/14/2012 |
| Notes: | |
| Project: | Humboldt Park Branch Library Addition |
| Address: | 1605 North Troy |
| Contractor: | Tyler Lane Construction, Inc |
| Amount: | 336534.57 |
| Reason: | Client Directed Change |
| Contract Number: | 1534 |
| Date: | 8/14/2012 |
| Notes: | |
| Architect of Record Named | |
| Project: | Nathan Hale Elementary School Linked Annex |
| Address: | 6140 South Melvina Avenue |
| Architect of Record Named: | ESA/Searl JV |
| Notes: | Architect of Record |
| Date: | 8/14/2012 |
| Project: | Edison Park Elementary School Linked Annex |
| Address: | 6220 North Olcott Avenue |
| Architect of Record Named: | Tripartite, Inc. |
| Notes: | Architect of Record |
| Date: | 8/14/2012 |
| Project: | Alexander Graham Bell Elementary School Addition |
| Address: | 3730 North Oakley Avenue |
| Architect of Record Named: | SMNG A (Schroeder Murchie Niemiec Gazda-Auskalnis Architects, Ltd.) |
| Notes: | Architect of Record |
| Date: | 8/14/2012 |
| Contract Amendments | |
| Project: | Program Management Office |
| Address: | 50 West Washington |
| Contractor Named: | The Rise Group, LLC |
| Notes: | Program Management Office |
| Amount: | 11000000.00 |
| Contract Number: | PS1398-A6 |
| Date: | 8/14/2012 |
| Project: | Brighton Park II Elementary School |
| Address: | 2611 West 48th Street |
| Contractor Named: | Architrave, Ltd. |
| Notes: | Architect of Record |
| Amount: | 32483.00 |
| Contract Number: | PS1241-A3 |
| Date: | 8/14/2012 |
| Professional Services Contract | |
| Services: | Environmental Demolition/Renovation |
| Project: | Nathan Hale Elementary School Linked Annex |
| Address: | 6140 South Melvina Avenue |
| Contractor With: | Terracon Consultants, Inc. |
| Amount of Contract: | 20587.50 |
| Contract Number: | PS1651G-TO |
| Date: | 8/14/2012 |
| Services: | Material Testing Services |
| Project: | Ortiz de Dominquez Elementary School Artificial Turf |
| Address: | 3000 South Lawndale Avenue |
| Contractor With: | SEECO Consultants, Inc. |
| Amount of Contract: | 14354.00 |
| Contract Number: | PS1669F-TO |
| Date: | 8/14/2012 |
| Services: | Traffic Study Services |
| Project: | Edison Park Elementary School Linked Annex |
| Address: | 6220 North Olcott Avenue |
| Contractor With: | Alfred Benesch & Company |
| Amount of Contract: | 10000.00 |
| Contract Number: | PS1557B-TO |
| Date: | 8/14/2012 |
| Services: | Environmental ABC Services |
| Project: | Albany Park Branch Library |
| Address: | 5150 North Kimball Avenue |
| Contractor With: | V3 Companies of Illinois |
| Amount of Contract: | 209322.00 |
| Contract Number: | PS1569L-TO |
| Date: | 8/14/2012 |
| Services: | Environmental Demolition/Renovation |
| Project: | Alexander Graham Bell Elementary School Addition |
| Address: | 3730 North Oakley Avenue |
| Contractor With: | Environmental Design International, Inc. |
| Amount of Contract: | 15612.50 |
| Contract Number: | PS1651D-TO |
| Date: | 8/14/2012 |
| Services: | Term Agreement to provide playground equipment, design and certification of installation services. |
| Project: | Playground Equipment Term Agreement |
| Address: | Various Locations |
| Contractor With: | Leisure Products/Landscape Structures |
| Amount of Contract: | 2000000.00 |
| Contract Number: | PS1921A |
| Date: | 8/14/2012 |
| Services: | Term Agreement to provide playground equipment, design and certification of installation services. |
| Project: | Playground Equipment Term Agreement |
| Address: | Various Locations |
| Contractor With: | Game Time Division |
| Amount of Contract: | 2000000.00 |
| Contract Number: | PS1921B |
| Date: | 8/14/2012 |