LEED Certified: Silver
The Edgebrook Elementary School Addition Project consists of an approximately 36,000-square-foot addition to the existing school, removal of the existing modular classrooms, and removal and reconstruction of the playground and teachers parking lot. The project will provide the school with an additional 8 classrooms, a computer room, a science room, a new lunch room and warming kitchen, as well as an additional mechanical room and new chiller well.
LEED Features: Approximately 72% of the roof of the addition will be green roof, providing a 45% green roof for the entire roof area of the school.
Social Media:
- Follow this project on Twitter @PBCChi #Edgebrook
- More Pictures on Flickr
6525 North Hiawatha
Ward 45: Forest Glen
CONTRACT INFORMATION
General Contractors:
Henry Bros. Company
Contract:
- Pay Application #1 (8/9/11)
- Pay Application #2 (9/26/11)
- Pay Application #3 (10/12/11)
- Pay Application #4 (11/30/11)
- Pay Application #5 (12/21/11)
- Pay Application #6 (2/14/12)
- Pay Application #7 (2/27/12)
- Pay Application #8 (3/20/12)
- Pay Application #9 (4/12/12)
- Pay Application #10 (5/8/12)
- Pay Application #11 (5/25/11)
- Pay Application #12 (7/13/12)
- Pay Application #13 (8/15/12)
- Pay Application #13a (8/15/12)
- Pay Application #14 (8/31/12)
- Pay Application #15 (12/4/12)
- Pay Application #16 (12/4/12)
- Pay Application #17 (9/24/13) Final
Architect of Record:
Altus Works, Inc.
PROJECT DOCUMENTS
PRESS RELEASES
- Mayor Emanuel and CPS CEO Byrd-Bennett Announce Completion of Two Annexes to Alleviate Overcrowding At Two Neighborhood Elementary Schools
- Mayor Daley Visits Site of New Garvy Elementary School Addition on Northwest Sitde to Open in the Fall
- Contract Approved To Construct Edgebrook Elementary School Addition