Pursuant to Section 3.03 of the By-Laws of the Public Building Commission of Chicago, as amended, the regular meeting of the Board of Commissioners shall be held without notice at the Board Room, 2nd floor, Richard J. Daley Center, Chicago, Illinois, at 2:30 oâclock p.m. on the second Tuesday of each month (except for the month of October, in which month the annual meeting is held on October 1, unless the same shall be a legal holiday, in which event said meeting shall be held on the next succeeding business day).
Attachments |
Agenda | Minutes |
Other Actions | |
Action: | Resolution Commending Maria N. Saldana |
Details: | Adopted a resolution honoring Maria N. Saldana for her service to the PBC.
Download the resolution here . |
Date: | 1/08/2008 |
Action: | Administration of Oath of Office |
Details: | Gery J. Chico, appointee of the Chicago Park District for a term ending September 30, 2008. |
Date: | 1/08/2008 |
Action: | Bouchet Math & Science Academy Addition |
Details: | Approval of a request from the Chicago Public Schools for the PBC to provide formulation services associated with the conceptual development of a project budget and project schedule for the Bouchet Math and Science Academy Addition and Renovation Project located at 74th Street and South Jeffrey Avenue. |
Date: | 1/08/2008 |
Action: | Back of the Yards Area High School |
Details: | Approval of a request from the Chicago Public Schools for the PBC to provide formulation services associated with the conceptual development of a project budget and project schedule for the new Back of the Yards High School Project located at 47th and Hoyne. |
Date: | 1/08/2008 |
Action: | Pre-Qualified Contractors |
Details: | Report by the Executive Director on the general construction firms which have submitted qualifications to be pre-qualified for the following projects:
|
Date: | 1/08/2008 |
Contract Amendments | |
Project: | Engine 70 |
Address: | 6030 North Clark Street |
Contractor Named: | Bauer Latoza Studio |
Notes: | Architect of Record. |
Amount: | 5040.00 |
Contract Number: | PS814-A4 |
Date: | 1/08/2008 |
Project: | Belmont Cragin Area Elementary School |
Address: | Grand and Central |
Contractor Named: | STL Architects, Inc. |
Notes: | Architect of Record. |
Amount: | 80000.00 |
Contract Number: | PS1106 A1 |
Date: | 1/08/2008 |
Project: | Vehicle Maintenance Facility |
Address: | 5201 South Western Avenue |
Contractor Named: | Teng & Associates, Inc. |
Notes: | Architect of Record |
Amount: | 37645.00 |
Contract Number: | PS1022-A3 |
Date: | 1/08/2008 |
Professional Services Contract | |
Services: | Temp work for HR |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Account Temps |
Amount of Contract: | 1714.50 |
Contract Number: | PS930 |
Date: | 1/08/2008 |
Services: | Four laptop computers |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Systems Solutions, Inc. |
Amount of Contract: | 7216.00 |
Contract Number: | PS599 |
Date: | 1/08/2008 |
Services: | LEED Certification. |
Project: | Albany Park Multicultural Academy |
Address: | 4929 North Sawyer Avenue |
Contractor With: | U.S. Green Building Council |
Amount of Contract: | 4692.78 |
Contract Number: | PS1205 |
Date: | 1/08/2008 |
Services: | ALTA Survey |
Project: | Ogden Replacement Elementary School |
Address: | 24 West Walton |
Contractor With: | Land Surveying Services |
Amount of Contract: | 9340.00 |
Contract Number: | PS1143 |
Date: | 1/08/2008 |
Services: | ALTA Survey |
Project: | Engine 109 |
Address: | 2215-2359 South Kedzie |
Contractor With: | Land Surveying Services |
Amount of Contract: | 6000.00 |
Contract Number: | PS1189 |
Date: | 1/08/2008 |
Services: | ALTA Survey |
Project: | Greater Grand Crossing Branch Library |
Address: | 73rd & Ellis |
Contractor With: | Alfred Benesch & Company |
Amount of Contract: | 7640.00 |
Contract Number: | PS1202 |
Date: | 1/08/2008 |
Services: | Environmental Phase II Site Assessment |
Project: | Back of the Yards Area High School |
Address: | 47th & Hoyne |
Contractor With: | GSG Consultants, Inc. |
Amount of Contract: | 132860.00 |
Contract Number: | PS1179 |
Date: | 1/08/2008 |
Services: | Project close out. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Washington, Pittman & McKeever |
Amount of Contract: | 25000.00 |
Contract Number: | PS1212 |
Date: | 1/08/2008 |
Services: | |
Project: | Dunning Branch Library |
Address: | |
Contractor With: | EDI (Environmental Design International) |
Amount of Contract: | 7700.00 |
Contract Number: | PS1200 |
Date: | 1/08/2008 |
Services: | Environmental Site Assessment Services |
Project: | Eric Solorio Academy High School |
Address: | 5400 South St. Louis |
Contractor With: | GSG Consultants, Inc. |
Amount of Contract: | 1750.00 |
Contract Number: | PS1201 |
Date: | 1/08/2008 |
Services: | Appointed to provide leased vehicles. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Enterprise Leasing Company |
Amount of Contract: | 0.00 |
Contract Number: | PS1139 |
Date: | 1/08/2008 |
Services: | Utilities |
Project: | 9th District Police Station |
Address: | 3120 South Halsted |
Contractor With: | People’s Gas Light & Coke Co. |
Amount of Contract: | 1967.00 |
Contract Number: | PS1192 |
Date: | 1/08/2008 |
Services: | Building Permit. |
Project: | Langston Hughes/Davis Developmental Elementary |
Address: | 240 West 104th Street |
Contractor With: | Department of Construction and Permit |
Amount of Contract: | 34621.00 |
Contract Number: | PS1208 |
Date: | 1/08/2008 |
Services: | Utilities |
Project: | Beverly Branch Library |
Address: | 1962 West 95th Street |
Contractor With: | A.T.&T. |
Amount of Contract: | 41186.30 |
Contract Number: | PS1074 |
Date: | 1/08/2008 |
Services: | Utilities |
Project: | Engine Company 88 |
Address: | 3637 West 59th Street |
Contractor With: | OEMC |
Amount of Contract: | 147376.00 |
Contract Number: | PS1195 |
Date: | 1/08/2008 |
Services: | Building Permit. |
Project: | Mark T. Skinner School |
Address: | 1260 West Adams |
Contractor With: | Department of Construction and Permit |
Amount of Contract: | 35224.00 |
Contract Number: | PS1207 |
Date: | 1/08/2008 |
Change Order Approved | |
Project: | South Water Purification Plant Chlorine Improvements |
Address: | 3300 East Cheltenham Place |
Contractor: | The George Sollitt Construction Company |
Amount: | 12183.00 |
Reason: | Discovered Condition |
Contract Number: | 1339 |
Date: | 1/08/2008 |
Notes: | |
Project: | Edna White Community Garden |
Address: | 1900 West Monterey |
Contractor: | G. F. Structures Corporation |
Amount: | -7263.80 |
Reason: | Credit for Liquidated Damages |
Contract Number: | 1328 |
Date: | 1/08/2008 |
Notes: |