Pursuant to Section 3.03 of the By-Laws of the Public Building Commission of Chicago, as amended, the regular meeting of the Board of Commissioners shall be held without notice at the Board Room, 2nd floor, Richard J. Daley Center, Chicago, Illinois, at 2:30 oâclock p.m. on the second Tuesday of each month (except for the month of October, in which month the annual meeting is held on October 1, unless the same shall be a legal holiday, in which event said meeting shall be held on the next succeeding business day).
Attachments |
Agenda | Minutes |
Architect of Record Named | |
Project: | CPS High School Program |
Address: | Various Locations |
Architect of Record Named: | John Ronan Architects/DeStefano + Partners JV |
Notes: | Design Architect for the Chicago Public Schools High School Program (including)
|
Date: | 8/14/2007 |
Project: | Eric Solorio Academy High School |
Address: | 5400 South St. Louis Avenue |
Architect of Record Named: | John Ronan Architects/DeStefano + Partners JV |
Notes: | Architect of Record |
Date: | 8/14/2007 |
Project: | South Shore High School |
Address: | 75th & Jeffery |
Architect of Record Named: | John Ronan Architects/DeStefano + Partners JV |
Notes: | Architect of Record |
Date: | 8/14/2007 |
Other Actions | |
Action: | Assistant Secretary |
Details: | Accepted the resignation of Joseph Harmening as the Assistant Secretary of the the Public Building Commission of Chicago and nominated Patrick J. Harney as successor Assistant Secretary. |
Date: | 8/14/2007 |
Action: | Pre-Qualified Commissioning Services |
Details: | Six firms are recommended, including two MBE/WBE firms:
|
Date: | 8/14/2007 |
Action: | Pre-Qualified Environmental Testing & Consulting |
Details: | 21 firms are recommended, including four MBE/WBE firms:
|
Date: | 8/14/2007 |
Action: | Pre-Qualified Surveying Services |
Details: | 16 firms are recommended, including 10 MBE/WBE firms:
|
Date: | 8/14/2007 |
Action: | Pre-Qualified Construction Materials Testing Services |
Details: | Seven firms are recommended, including four MBE firms:
|
Date: | 8/14/2007 |
Contract Amendments | |
Project: | Columbus School Campus Park |
Address: | 1003 North Leavitt Street |
Contractor Named: | Land Design Collaborative, Inc. |
Notes: | Architect of Record. |
Amount: | 5093.75 |
Contract Number: | PS903-A1 |
Date: | 8/14/2007 |
Project: | Term Agreement |
Address: | Various Locations |
Contractor Named: | GSG Consultants, Inc. |
Notes: | Environmental remediation for Engine Company 102. |
Amount: | 298000.00 |
Contract Number: | PS979 |
Date: | 8/14/2007 |
Project: | 12th District Police Station |
Address: | 1400 Block of South Ashland |
Contractor Named: | R. M. Chin & Associates |
Notes: | Owner’s Representative. |
Amount: | 6000.00 |
Contract Number: | PS648 |
Date: | 8/14/2007 |
Change Order Approved | |
Project: | Albany Park School |
Address: | 4929 North Sawyer Avenue |
Contractor: | Pacific Construction Services, Inc. |
Amount: | 7938.69 |
Reason: | Omission |
Contract Number: | 1334 |
Date: | 8/14/2007 |
Notes: | |
Project: | Gale School Community Center |
Address: | 1610 West Howard |
Contractor: | FHP Tectonics Corp. |
Amount: | -477.00 |
Reason: | Error |
Contract Number: | 1336 |
Date: | 8/14/2007 |
Notes: | |
Project: | Daley College Title II ADA |
Address: | 7500 South Pulaski |
Contractor: | F.H. Paschen, S.N. Nielsen & Associates, LLC |
Amount: | -13183.70 |
Reason: | Credit for Liquidated Damages |
Contract Number: | 1301 |
Date: | 8/14/2007 |
Notes: | |
Professional Services Contract | |
Services: | Laptop computer. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Systems Solutions, Inc. |
Amount of Contract: | 1575.00 |
Contract Number: | PS599 |
Date: | 8/14/2007 |
Services: | Reproduction of documents for:
|
Project: | Various Projects |
Address: | Various Locations |
Contractor With: | Cushing and Company |
Amount of Contract: | 7336.97 |
Contract Number: | PS1129-30 |
Date: | 8/14/2007 |
Services: | Temp work for Finance Department. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Account Temps |
Amount of Contract: | 17076.70 |
Contract Number: | PS1070 |
Date: | 8/14/2007 |