Board Meeting – October 1, 2018


Event Details

  • Date:
  • Categories:

Second Floor Board Room
Richard J. Daley Center
50 West Washington Street

Board Material

Board Actions

Task Order Awarded
Project: Merlo Branch Library Renovation and Modernization
Company:  Ross Barney Architects
Task Order Number:   08305-PS3009-001
Task Order Amount: $386,500.00
Notes: Architect of Record
Task Order Awarded
Project: Read Dunning Salt Storage Structure
Company:  STL Architects, Inc.
Task Order Number:   04020-PS3002-002
Task Order Amount: $7,500.00
Notes: Architect of Record
Professional Service Agreements 
Service: Comprehensive Digital Construction Document Printing
Project: Program-wide
Company: Aloha Document Services, Inc. dba Aloha Print Group
Contract Number:   PS3001
Contract Amount: NTE: $500,000.00
Notes:
Professional Service Agreements 
Service: Comprehensive Digital Construction Document Printing
Project: Program-wide
Company: Cross Rhodes Reprographics
Contract Number:   PS3001
Contract Amount: NTE: $500,000.00
Notes:
Professional Service Agreements 
Service: Comprehensive Digital Construction Document Printing
Project: Program-wide
Company: Cushing and Company
Contract Number:   PS3001
Contract Amount: NTE: $500,000.00
Notes:
Professional Service Agreements 
Service: Construction Cost Estimating
Project: Program-wide
Company: CCS International, Inc.
Contract Number:   PS3008
Contract Amount: NTE: $1,500.000.00
Notes:
Professional Service Agreements 
Service: Construction Cost Estimating
Project: Program-wide
Company: Rider Levett Bucknall
Contract Number:   PS3008
Contract Amount: NTE: $1,500.000.00
Notes:
Professional Service Agreements 
Service: Construction Cost Estimating
Project: Program-wide
Company: Vistara Construction Services
Contract Number:   PS3008
Contract Amount: NTE: $1,500.000.00
Notes:
Professional Service Agreements 
Service: Construction Cost Estimating
Project: Program-wide
Company: The Concord Group
Contract Number:   PS3008
Contract Amount: NTE: $1,500.000.00
Notes:
Change Order Approved
Project: Ebinger Elementary School Site Prep
Contractor: Friedler Construction Co.
Contract Number:   C1585
Change Order Amount:  ($49,063.00)
Reason for Change Order: Other
Notes: Deduct unused commission contingency
Change Order Approved
Project: Abraham Lincoln Elementary School Annex
Contractor: Blinderman Meccor JV
Contract Number:   C1561
Change Order Amount:  ($12,618.00)
Reason for Change Order: Other
Notes: Liquidated Damages Credit
Change Order Approved
Project: Minnie Mars Jamieson Elementary School Annex
Contractor: Old Veteran Construction, Inc.
Contract Number:   C1567
Change Order Amount:  $157,068.00
Reason for Change Order: Other
Notes: Site restoration at south playlot and deduct unused site work allowance.
Partial Undertaking Request
Action:  Approval of a Partial Undertaking Request for the delivery of twelve school projects.
Brooks College Prep Academy Turf Field Repairs

Corliss High School Renovation

Dore Elementary School Pre-K Expansion

Kenwood Academy High School Renovation

Locke Elementary School Renovation

Lovett Elementary School Renovation

Phillips Academy High School Athletic Amenities

Prosser Career Academy Renovation

Washington High School Renovation

Rickover High School Education Program

New Belmont Cragin Replacement School

New Hancock Replacement School

Revised Undertaking Request
Action:  Approval of a Revised Undertaking Request from the Board of Education for the William Jones College Preparatory High School Project located at 700 South State Street.
Revised Undertaking Request
Action: Approval of a Revised Undertaking Request from the City of Chicago for the Read Dunning Salt Storage Structure Project located at 4121 North Oak Park Avenue.
Commissioner Appointment
Name:  Frank M. Clark
Appointment:  Commissioner of the PBC
Term End Date:   September 30, 2023
Notes:  Administration of the Oath of Office
Commissioner Appointment
Name:  Jesse H. Ruiz
Appointment:  Commissioner of the PBC
Term End Date:   September 30, 2023
Notes:  Administration of the Oath of Office
Action: Report regarding the Guaranteed Maximum Price (GMP) agreement for Design-Build services for the  South Side High School Project
Company Power/Ujamaa II, a Project Specific Joint Venture
Amount GMP Value: $76,366,713
Action: Approval of the Public Building Commission’s 2019 Administrative Budget.
Action: Approval of the proposed Richard J. Daley Center 2019 Operating and Capital Budget.