Board Meeting – August 08, 2017


Event Details

  • Date:
  • Categories:

Second Floor Board Room, Richard J. Daley Center, 50 W. Washington Street

Attachments
Agenda | Presentation | Summary | Minutes
General Contractor Named
Project: Dore Elementary School
Address: 7134 West 65th Street
Contractor Named: Sollitt/Oakley JV
Notes:
Contract For: 30442000.00
Date: 8/08/2017
Contract Number: C1577R
Project: Chicago Park District Capital Improvement Program
Address: 50 W Washington
Contractor Named:
Notes: View the full list of Prequalified General Contractors here.
Contract For: 0.00
Date: 8/08/2017
Contract Number:
Project: Skinner West Elementary School Annex
Address: 1260 W Adams
Contractor Named: F.H. Paschen, S.N. Nielsen & Associates, LLC
Notes:
Contract For: 11804000.00
Date: 8/08/2017
Contract Number: C1579
Professional Services Contract
Services: Environmental Engineering
Project: Read Dunning Middle School
Address: 4001 N Oak Park Ave
Contractor With: GSG Consultants, Inc.
Amount of Contract: 586248.00
Contract Number: PS2060F-TO
Date: 8/08/2017
Services: Traffic Study Services
Project: Ebinger Elementary School Annex
Address: 7350 W Pratt Ave
Contractor With: DLZ Illinois, Inc.
Amount of Contract: 16608.00
Contract Number: PS2064B-TO
Date: 8/08/2017
Services: Traffic Study Services
Project: Mt. Greenwood Elementary School Annex II
Address: 10841 S Homan Avenue
Contractor With: DLZ Illinois, Inc.
Amount of Contract: 17988.00
Contract Number: PS2064B-TO
Date: 8/08/2017
Services: Traffic Study Services
Project: Prussing Elementary School Annex
Address: 4650 N Menard Ave
Contractor With: Terra Engineering, Ltd.
Amount of Contract: 13970.00
Contract Number: PS2064F-TO
Date: 8/08/2017
Services: Environmental Engineering
Project: South Side High School
Address: 6835 S Normal
Contractor With: Environmental Design International, Inc.
Amount of Contract: 174388.50
Contract Number: PS2060E-TO
Date: 8/08/2017
Services: Cardno, Inc. will provide subsurface utility investigation services.
Project: Read Dunning Middle School
Address: 4001 N Oak Park Ave
Contractor With: Cardno, Inc.
Amount of Contract: 23600.00
Contract Number: PS2097
Date: 8/08/2017
Services: Traffic Study Services
Project: Esmond Elementary School Annex
Address: 1865 W Montvale Ave
Contractor With: Primera Engineers, Ltd.
Amount of Contract: 16580.00
Contract Number: PS2064E-TO
Date: 8/08/2017
Other Actions
Action: Lincoln Elementary School Annex
Details: Approval of a Revised Undertaking Request from the Board of Education for the Abraham Lincoln Elementary School Annex Project located at 615 West Kemper Place.
Date: 8/08/2017
Action: Chicago Transit Authority Projects
Details: Approval of an Undertaking Request from the Chicago Transit Authority for the following projects:

  • 77th Street Bus Garage Washer and High Speed Door Project located at 210 W 79th Street (Ward 17)
  • Kedzie Bus Garage High Speed Door Project located at 358 S Kedzie Avenue (Ward 28)

Chicago Transit Authority has assigned the contractor, John Burns Construction, to the PBC.

Date: 8/08/2017
Action: Revised OEMC Undertakings
Details: Approval of Revised Undertakings from the City of Chicago Office of Emergency Management and Communications:

  • Undertaking 102
  • Undertaking 118
Date: 8/08/2017
Action: Report by the Executive Director
Details: Report by the Executive Director regarding the assignment of Professional Service Contract 1994 with Ardmore Associates to Ardmore Roderick for Project Development Services.
Date: 8/08/2017
Change Order Approved
Project: Lincoln Elementary School Annex
Address: 615 W Kemper
Contractor: Blinderman Meccor JV
Amount: 373919.36
Reason: Multiple see below
Contract Number: C1561
Date: 8/08/2017
Notes:
  • Weather and Utility Delays
  • Deduct unused Commission’s Contingency