Attachments |
Agenda | Summary | Minutes |
Other Actions | |
Action: | Board of Education Playground Equipment |
Details: | Approval of an undertaking request from the Board of Education for the purchase of playground equipment at the following schools:
|
Date: | 6/08/2010 |
Action: | Ford Calumet Environmental Center |
Details: | Approval of a formulation request from the City of Chicago Department of Environment for the Ford Calumet Environmental Center located in the vicinity of 130th and Torrance Avenue |
Date: | 6/08/2010 |
Action: | Humboldt Park |
Details: | Approval of an undertaking request from the Chicago Park for the purchase of playground equipment at Humboldt Park, 1440 North Sacramento Avenue. |
Date: | 6/08/2010 |
Action: | Audit Committee |
Details: | Accepted a report by the Audit Committee Chairman regarding meeting held on June 3, 2010. |
Date: | 6/08/2010 |
Action: | Prevailing Wage Rates |
Details: | Approval of the June 2010 Prevailing Wage Rates for construction work on PBC projects as determined by the Illinois Department of Labor. |
Date: | 6/08/2010 |
Action: | Collins High School Renovation Project |
Details: | Approval of an undertaking request from the Board of Education for the Collins High School Renovation Project located at 1312 South Sacramento Drive. |
Date: | 6/08/2010 |
Action: | Air Force Academy Renovation Project |
Details: | Approval of an undertaking request from the Board of Education for the Air Force Academy Renovation Project located at 3630 South Wells. |
Date: | 6/08/2010 |
Action: | Chicago Arts High School Renovation Project |
Details: | Approval of an undertaking request from the Board of Education for the Chicago Arts High School Renovation Project located at 2714 West Augusta Boulevard. |
Date: | 6/08/2010 |
Action: | Engine Company 16 |
Details: | Approval of an undertaking request from the City of Chicago for the design and construction of the Engine Company 16 Firehouse located at 3901 South Wabash Avenue. |
Date: | 6/08/2010 |
Action: | CPS Security Camera Project |
Details: | Approval of an undertaking request from the City of Chicago for for the CPS Security Camera Project. |
Date: | 6/08/2010 |
Action: | William Jones College Preparatory High School |
Details: | Approval to appoint Bovis Lend Lease as Construction Manager at Risk for the Jones College Prep High School Project located at 606 South State Street. |
Date: | 6/08/2010 |
Contract Amendments | |
Project: | Greater Grand Crossing Branch Library |
Address: | 1000 East 73rd Street |
Contractor Named: | Lohan Anderson |
Notes: | Architect of Record |
Amount: | 8585.00 |
Contract Number: | PS1458-A1 |
Date: | 6/08/2010 |
Project: | Valley Forge Park Fieldhouse |
Address: | 7001 West 59th Street |
Contractor Named: | Booth Hansen, Ltd. |
Notes: | Architect of Record |
Amount: | 2675.00 |
Contract Number: | PS1102-A4 |
Date: | 6/08/2010 |
Project: | Program Management Office |
Address: | Various Locations |
Contractor Named: | The Rise Group, LLC |
Notes: | Program Management Office |
Amount: | 4300000.00 |
Contract Number: | PS1398-A2 |
Date: | 6/08/2010 |
Project: | Michael Reese Hospital Campus |
Address: | 2929 South Ellis |
Contractor Named: | Carnow Conibear & Assoc., Ltd. |
Notes: | General Environmental Manager |
Amount: | 115440.00 |
Contract Number: | PS1162-A2 |
Date: | 6/08/2010 |
Project: | 23rd District Police Station |
Address: | 850 West Addison |
Contractor Named: | Wight & Company |
Notes: | Architect of Record |
Amount: | 2400.00 |
Contract Number: | PS1039-A3 |
Date: | 6/08/2010 |
General Contractor Named | |
Project: | Marvin Camras Elementary School Renovation |
Address: | 3000 North Mango Avenue |
Contractor Named: | Tropic Construction Corporation |
Notes: | MBE Commitment: 28.4% WBE Commitment: 4.3% MBE Contractor & Sub-Contractors:
WBE Sub-Contractors:
|
Contract For: | 6021225.00 |
Date: | 6/08/2010 |
Contract Number: | 1513 |
Contract: | |
Project: | Ogden Elementary School |
Address: | 24 West Walton |
Contractor Named: | Mr. David’s Carpet Services, Ltd |
Notes: | Bid Package 22: Ceramic & Quarry Tile. Contract assigned to Turner Construction Company MBE Commitment: 25% WBE Commitment: 5% MBE Sub-Contractors:
WBE Sub-Contractors:
|
Contract For: | 84633.00 |
Date: | 6/08/2010 |
Contract Number: | 1668-22 |
Contract: | |
Project: | Sauganash Elementary School Addition |
Address: | 6040 North Kilpatrick |
Contractor Named: | Blinderman Construction Company, Inc. |
Notes: | MBE Commitment: 24% WBE Commitment: 4% MBE Sub-Contractors:
WBE Sub-Contractors:
|
Contract For: | 10525134.00 |
Date: | 6/08/2010 |
Contract Number: | 1512 |
Contract: | |
Project: | Garvy Elementary School Addition |
Address: | 5225 North Oak Park Avenue |
Contractor Named: | Skender Construction Company |
Notes: | MBE Commitment: 25.13% WBE Commitment: 6.3% MBE Sub-Contractors:
WBE Sub-Contractors:
|
Contract For: | 9490135.00 |
Date: | 6/08/2010 |
Contract Number: | 1511 |
Contract: | |
Project: | Ogden Elementary School |
Address: | 24 West Walton |
Contractor Named: | Schindler Elevators |
Notes: | Bid Package 33: Elevators. Contract assigned to Turner Construction Company MBE Commitment: 15% WBE Commitment: 0% MBE Sub-Contractors:
|
Contract For: | 349500.00 |
Date: | 6/08/2010 |
Contract Number: | 1668-33 |
Contract: | |
Project: | Ogden Elementary School |
Address: | 24 West Walton |
Contractor Named: | Floors Incorporated |
Notes: | Bid Package 24: Wood flooring/Stripping. Contract assigned to Turner Construction Company MBE Commitment: 0% WBE Commitment: 0% |
Contract For: | 81800.00 |
Date: | 6/08/2010 |
Contract Number: | 1668-24 |
Contract: | |
Project: | Ogden Elementary School |
Address: | 24 West Walton |
Contractor Named: | Flooring Resources |
Notes: | Bid Package 25: Resilient Flooring/Carpet. Contract assigned to Turner Construction Company MBE Commitment: 25% WBE Commitment: 10% MBE Sub-Contractors:
WBE Sub-Contractors:
|
Contract For: | 152443.00 |
Date: | 6/08/2010 |
Contract Number: | 1668-25 |
Project: | Ogden Elementary School |
Address: | 24 West Walton |
Contractor Named: | Abbey Paving and Sealcoating Co., Inc. |
Notes: | Bid Package 20: Asphalt Paving. Contract assigned to Turner Construction Company MBE Commitment: 0% WBE Commitment: 0% |
Contract For: | 42310.00 |
Date: | 6/08/2010 |
Contract Number: | 1668-20 |
Contract: | |
Project: | Ogden Elementary School |
Address: | 24 West Walton |
Contractor Named: | Poblocki Sign Company |
Notes: | Bid Package 29: Signage. Contract assigned to Turner Construction Company MBE Commitment: 54.9% WBE Commitment: 0% MBE Sub-Contractors:
|
Contract For: | 92000.00 |
Date: | 6/08/2010 |
Contract Number: | 1668-29 |
Contract: | |
Professional Services Contract | |
Services: | Phase II Environmental and Environmental Design Services |
Project: | Chicago Park District Park 484 |
Address: | 4701 West 67th Street |
Contractor With: | Carnow Conibear & Assoc., Ltd. |
Amount of Contract: | 31296.00 |
Contract Number: | PS1784 |
Date: | 6/08/2010 |
Services: | Material Testing |
Project: | Marquette Park Playground |
Address: | 6743 South Kedzie Ave |
Contractor With: | Terracon Consultants, Inc. |
Amount of Contract: | 4780.00 |
Contract Number: | PS1813 |
Date: | 6/08/2010 |
Services: | Material Testing |
Project: | Holmes Elementary School |
Address: | 955 West Garfield Blvd |
Contractor With: | K & S Engineers, Inc. |
Amount of Contract: | 13425.00 |
Contract Number: | PS1810 |
Date: | 6/08/2010 |
Services: | Re-Wiring of 2nd Floor |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Unisys |
Amount of Contract: | 8976.00 |
Contract Number: | PS743 |
Date: | 6/08/2010 |
Services: | Environmental Design and Phase II Environmental Services |
Project: | Peck Elementary School |
Address: | 3826 West 58th Street |
Contractor With: | Camp Dresser & McKee, Inc. |
Amount of Contract: | 41569.00 |
Contract Number: | PS1780 |
Date: | 6/08/2010 |
Services: | Material Testing |
Project: | Piotrowski Park Playground |
Address: | 4247 West 31st Street |
Contractor With: | Terracon Consultants, Inc. |
Amount of Contract: | 4780.00 |
Contract Number: | PS1812 |
Date: | 6/08/2010 |
Services: | Material Testing |
Project: | Chicago Park District Park 484 |
Address: | 4701 West 67th Street |
Contractor With: | Terracon Consultants, Inc. |
Amount of Contract: | 21205.00 |
Contract Number: | PS1797 |
Date: | 6/08/2010 |
Services: | Purchase of Printer and Wireless Remote for Projector |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | CDW-G |
Amount of Contract: | 233.84 |
Contract Number: | PS775 |
Date: | 6/08/2010 |
Services: | Provide Caisson Installation Observations and Reporting |
Project: | Little Village Library |
Address: | 2311 South Kedzie Ave. |
Contractor With: | Wang Engineering |
Amount of Contract: | 20977.00 |
Contract Number: | PS1807 |
Date: | 6/08/2010 |
Services: | Phase II Environmental-Additional Services |
Project: | Gwendolyn Brooks College Preparatory Academy |
Address: | 250 East 111th Street |
Contractor With: | Carnow Conibear & Assoc., Ltd. |
Amount of Contract: | 119700.00 |
Contract Number: | PS1539-A1 |
Date: | 6/08/2010 |
Services: | Phase II Environmental and Environmental Design Services |
Project: | Burroughs Elementary School Artificial Turf |
Address: | 3542 South Washtenaw |
Contractor With: | GSG Consultants, Inc. |
Amount of Contract: | 16420.00 |
Contract Number: | PS1811 |
Date: | 6/08/2010 |
Services: | All in one Printer/Copier/Fax |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Systems Solutions, Inc. |
Amount of Contract: | 879.00 |
Contract Number: | PS599-059 |
Date: | 6/08/2010 |
Services: | Pilot program to establish reporting templates and provide community hiring monitoring services |
Project: | Community Hiring Consulting Services |
Address: | 50 West Washington |
Contractor With: | Trinal, Inc. |
Amount of Contract: | 20000.00 |
Contract Number: | PS1837 |
Date: | 6/08/2010 |
Services: | Comprehensive consulting services regarding the planning for a portion of the school |
Project: | William Jones College Preparatory High School |
Address: | 606 South State Street |
Contractor With: | Chicago Realty Company |
Amount of Contract: | 24500.00 |
Contract Number: | PS1830 |
Date: | 6/08/2010 |
Services: | Surveying-Additional Services |
Project: | Back of the Yards High School |
Address: | 2111 West 47th Street |
Contractor With: | Chicago Guarantee Survey Company |
Amount of Contract: | 2795.00 |
Contract Number: | PS1194-A1 |
Date: | 6/08/2010 |
Services: | Phase II Environmental and Environmental Design Services |
Project: | Marvin Camras Elementary School Renovation |
Address: | 3000 North Mango Avenue |
Contractor With: | GSG Consultants, Inc. |
Amount of Contract: | 64490.00 |
Contract Number: | PS1804 |
Date: | 6/08/2010 |
Services: | Commissioning |
Project: | Haas Park Fieldhouse |
Address: | 2404 North Washtenaw |
Contractor With: | Primera Engineers, Ltd. |
Amount of Contract: | 35730.00 |
Contract Number: | PS1802 |
Date: | 6/08/2010 |
Services: | Financial Advisory Services |
Project: | Ford Calumet Environmental Center |
Address: | 130th and Torrance Avenue |
Contractor With: | Loop Capital Markets, LLC |
Amount of Contract: | 300000.00 |
Contract Number: | PS1849 |
Date: | 6/08/2010 |
Services: | Specialty Consultant and Inspection Services |
Project: | 31st Street Harbor Project (Coastal) |
Address: | 3155 South Lake Shore Drive |
Contractor With: | W.F. Baird & Associates Ltd |
Amount of Contract: | 288425.00 |
Contract Number: | PS1832 |
Date: | 6/08/2010 |
Change Order Approved | |
Project: | Valley Forge Park Fieldhouse |
Address: | 7001 West 59th Street |
Contractor: | Leopardo Companies |
Amount: | 257012.00 |
Reason: | Client Directed Change |
Contract Number: | 1493 |
Date: | 6/08/2010 |
Notes: | |
Project: | 41st Street Beach House |
Address: | 4101 South Lake Shore Drive |
Contractor: | Pacific Construction Services, Inc. |
Amount: | 19293.00 |
Reason: | |
Contract Number: | 1497A |
Date: | 6/08/2010 |
Notes: | |
Project: | Kathy Osterman Beach House |
Address: | 5701 North Lake Shore Drive |
Contractor: | Pacific Construction Services, Inc. |
Amount: | 20734.00 |
Reason: | |
Contract Number: | 1497B |
Date: | 6/08/2010 |
Notes: | |
Project: | Boone Clinton Elementary School |
Address: | 6700 North Whipple |
Contractor: | George Sollitt Construction/Oakley Construction JV |
Amount: | -124182.00 |
Reason: | Other |
Contract Number: | 1477 |
Date: | 6/08/2010 |
Notes: | |
Architect of Record Named | |
Project: | Engine Company 16 |
Address: | 3901 South Wabash Avenue |
Architect of Record Named: | InterActive Design, Inc. |
Notes: | Architect of Record |
Date: | 6/08/2010 |