Attachments |
Agenda | Minutes |
Professional Services Contract | |
Services: | Consulting services related to a Quarterly Review of PBC Internal Controls. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Prado & Renteria, Certified Public Accountants, Prof. Corp. |
Amount of Contract: | 22880.00 |
Contract Number: | PS1311B |
Date: | 7/08/2008 |
Services: | Consulting services related to PBC Policy and Procedure Development. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Bronner Group, LLC |
Amount of Contract: | 113400.00 |
Contract Number: | PS1311A |
Date: | 7/08/2008 |
Services: | Program Management Office Services to the PBC. |
Project: | Program Management Office (PMO) |
Address: | 50 West Washington |
Contractor With: | The Rise Group, LLC |
Amount of Contract: | 25300000.00 |
Contract Number: | PS1398 |
Date: | 7/08/2008 |
Services: | Temporary staffing work for Purchasing. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Account Temps |
Amount of Contract: | 1146.60 |
Contract Number: | PS |
Date: | 7/08/2008 |
Services: | Temporary staffing work for Purchasing. |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | Ajilon Professional Staffing |
Amount of Contract: | 834.57 |
Contract Number: | PS |
Date: | 7/08/2008 |
Services: | Purchase of AutoCad Software |
Project: | PBC Administration |
Address: | 50 West Washington |
Contractor With: | CDW-G |
Amount of Contract: | 2432.99 |
Contract Number: | PS775 |
Date: | 7/08/2008 |
Services: | ALTA Survey. |
Project: | Peck Elementary School Addition |
Address: | 3826 West 58th Street |
Contractor With: | Tecma Associates |
Amount of Contract: | 8400.00 |
Contract Number: | PS1314 |
Date: | 7/08/2008 |
Services: | Construction Material Testing |
Project: | Langston Hughes/Davis Developmental Elementary |
Address: | 240 West 104th Street |
Contractor With: | Flood Test Lab, Inc. (FTL) |
Amount of Contract: | 149152.00 |
Contract Number: | PS1264 |
Date: | 7/08/2008 |
Services: | Construction Material Testing |
Project: | Irene C. Hernandez Middle School |
Address: | 3510 West 55th Street |
Contractor With: | K & S Engineers, Inc. |
Amount of Contract: | 107689.00 |
Contract Number: | PS1295 |
Date: | 7/08/2008 |
Services: | Construction Material Testing |
Project: | Belmont Cragin Area Elementary School |
Address: | 2231 North Central Avenue |
Contractor With: | Terracon Consultanting Engineers & Scientists. |
Amount of Contract: | 73530.00 |
Contract Number: | PS1286 |
Date: | 7/08/2008 |
Services: | Construction Material Testing |
Project: | New Westinghouse High School |
Address: | Franklin & Kedzie |
Contractor With: | GSG Consultants, Inc. |
Amount of Contract: | 15590.00 |
Contract Number: | PS1281 |
Date: | 7/08/2008 |
Services: | Phase I Environmental ESA |
Project: | Brighton Park II Area Elementary |
Address: | 48th & Rockwell |
Contractor With: | K + Environmental Services, L.L.C. |
Amount of Contract: | 1950.00 |
Contract Number: | PS1282 |
Date: | 7/08/2008 |
Services: | Legal Survey & Legal Description |
Project: | Mariano Azuela Elementary School |
Address: | 4707 West Marquette Road |
Contractor With: | Professional Land & Construction Surveyrs – Gremley & Biedermann, Inc. |
Amount of Contract: | 3000.00 |
Contract Number: | PS1299 |
Date: | 7/08/2008 |
Services: | Phase II Environmental ESA |
Project: | South Shore High School |
Address: | 75th & Jeffery |
Contractor With: | GSG Consultants, Inc. |
Amount of Contract: | 73200.00 |
Contract Number: | PS1304 |
Date: | 7/08/2008 |
Services: | Phase II Environmental ESA |
Project: | Taylor-Lauridsen Park & Fieldhouse |
Address: | 704 West 42nd Street |
Contractor With: | Carnow Conibear & Assoc., Ltd. |
Amount of Contract: | 85880.00 |
Contract Number: | PS1328 |
Date: | 7/08/2008 |
Services: | Phase II Environmental ESA |
Project: | Jesse Owens Park & Fieldhouse |
Address: | 8800 South Clyde Avenue |
Contractor With: | CDM Smith |
Amount of Contract: | 59070.00 |
Contract Number: | PS |
Date: | 7/08/2008 |
Services: | JOC contract management. |
Project: | West Ridge Elementary School |
Address: | 6700 North Whipple |
Contractor With: | The Gordian Group, Inc. |
Amount of Contract: | 4057.80 |
Contract Number: | PS1007 |
Date: | 7/08/2008 |
Services: | Storm Water NOI |
Project: | Langston Hughes/Davis Developmental Elementary |
Address: | 240 West 104th Street |
Contractor With: | Illinois Environmental Protection Agency |
Amount of Contract: | 500.00 |
Contract Number: | PS1337 |
Date: | 7/08/2008 |
Services: | Utility |
Project: | Beverly Branch Library |
Address: | 1962 West 95th Street |
Contractor With: | People’s Gas Light & Coke Co. |
Amount of Contract: | 1153.00 |
Contract Number: | PS1362 |
Date: | 7/08/2008 |
Services: | Storm Water NOI |
Project: | Mark T. Skinner School |
Address: | 1260 West Adams |
Contractor With: | Illinois Environmental Protection Agency |
Amount of Contract: | 500.00 |
Contract Number: | PS1338 |
Date: | 7/08/2008 |
Other Actions | |
Action: | Southeast Area High School |
Details: | Approval of a request from the Board of Education to designate property bounded by 86th Street on the north, Greenbay on the east, 87th Street on the south and Burley Avenue on the west for a new Southeast Area High School. |
Date: | 7/08/2008 |
Change Order Approved | |
Project: | Engine 18 |
Address: | 1360 South Blue Island |
Contractor: | The Lombard Company |
Amount: | -188472.00 |
Reason: | Multiple see below |
Contract Number: | 1453 |
Date: | 7/08/2008 |
Notes: |
|
Project: | Beverly Branch Library |
Address: | 1962 West 95th Street |
Contractor: | Blinderman Construction Company, Inc. |
Amount: | 0.00 |
Reason: | Error or Omission |
Contract Number: | 1459 |
Date: | 7/08/2008 |
Notes: | Time extension |
Project: | Gale School Community Center |
Address: | 1610 West Howard |
Contractor: | FHP Tectonics Corp. |
Amount: | 51130.00 |
Reason: | Other |
Contract Number: | 1336 |
Date: | 7/08/2008 |
Notes: | |
General Contractor Named | |
Project: | Norwood Park Senior Satellite Center |
Address: | 5801 North Natoma Avenue |
Contractor Named: | Oakley Construction Co. |
Notes: | MBE Commitment: 26.92% WBE Commitment: 5.28%
MBE Contractor & Sub-Contractors:
WBE Sub Contractors:
|
Contract For: | 2310250.00 |
Date: | 7/08/2008 |
Contract Number: | 1468 |
Contract: | |
Project: | West Ridge Elementary School |
Address: | 6700 North Whipple |
Contractor Named: | Rossi Contractors, Inc. |
Notes: | Job Order Contracting: Site Security, Asbestos Survey, and Exploratory Trenching MBE: 70.61% WBE: 5.33% MBE Sub-Contractors:
WBE Sub Contractors:
|
Contract For: | 36889.10 |
Date: | 7/08/2008 |
Contract Number: | 1461 |